West Toronto Diamond Grade Separation
West Toronto Diamond Grade Separation
Community Updates
Community Update -- August 23, 2010
There are approximately 50 piles left to be installed under
the current pile installation contract at the West Toronto Diamond.
Since June 29, an extended full road closure has been in
place to allow for the installation of piles on the centre wall and to complete
the temporary restoration of a short segment of road across the railway corridor
(intersection of Old Weston Road and Junction Road). This road closure is
required for safety reasons to accommodate all types of construction equipment
in full operation across this intersection, and includes closure to pedestrian
access. It is anticipated that the roadway will be restored, and will re-open
for vehicle and pedestrian traffic, in late September 2010. We apologize for the
inconvenience as this work is completed as quickly and safely as possible.
The next contract will begin late Fall/early Winter and
will primarily consist of drilling out the soil from within the piles and
interlocks and then filling them with concrete and other sealing materials. It
is also anticipated that some piles will also need to be replaced during this
contract. More detailed information about the scope and impacts of next contract
will be provided by Fall 2010.
For more information about the overall project at West
Toronto Diamond, please visit the links below or call the office at
416-604-9582.
About the West Toronto Diamond Grade Separation
The West
Toronto Diamond is part of the Georgetown South Corridor, one of the most
exciting transit projects in the GTA. It will enable a new link from Union
Station to Pearson Airport, and will support expanded service to
Kitchener-Waterloo, Brampton, and Mississauga.
Basically, we
are building an underpass to separate two major rail corridors - right now we
have the equivalent of two major highways meeting at a traffic light. This hurts
our ability to provide reliable service for our customers.
Since June
2009, we changed the way we were working in order to reduce the noise,
implementing the use of impact hammers equipped with sound mitigation as well as
bringing in quieter piling technology from France and Japan. As a result of
these efforts the noise from our work was cut in half.
In early
December, 2009, the Canadian Transportation Agency (CTA) asked for additional
measures, including better information and monitoring of piling activity. In
addition to the earlier measures we implemented in June, we also incorporated
these additional requirements.
Today, we are in full compliance
with the CTA's ruling. There are fewer than 60 piles left to be installed.
Project description, improvements and location
Project Description
The West Toronto Diamond project will separate Canadian Pacific Railway's
North Toronto freight line from GO's Weston Subdivision (Georgetown line). The
north-south tracks to and from Georgetown will be lowered so that they run under
CPR's North Toronto line.
Improvements:
- More reliable GO service by eliminating the need to accommodate both
freight and GO trains at this crossing point.
- Less pollution and noise for residents due to fewer trains stopping and
idling in the neighbourhood, and commuter traffic running through the
lowered corridor.
- Less noise and whistling from trains crossing the West Toronto Diamond.
- Increased train service for northwest Toronto and Peel Region.
Location: The Junction area in Toronto, where Old Weston
Road cross the rail tracks.
Project area map, schedule, updates and schedule archive
Project area map

Legend
G - Giken
I - Impact Hammer
V - PTC Vibro Hammer
M - Moveable Sound Barrier
(#) - Total piles driven each
day
Project schedule
| |
Mon
Aug 30 |
Tue
Aug 31 |
Wed
Sept 1 |
Thurs
Sept 2 |
Fri Sept 3 |
Sat
Sept 4 |
Sun
Sept 5 |
| Zone A |
|
|
|
|
|
No activity |
No activity |
| Zone B |
|
|
|
|
|
| Zone C |
I
V
|
I
V
|
I
V
|
I
V
|
I
V
|
| Zone D |
V
G
(2) |
V
G |
V
G |
V
G |
V
G |
| |
Mon
Sept 6 |
Tues
Sept 7 |
Wed
Sept 8 |
Thurs
Sept 9 |
Fri Sept 10 |
Sat
Sept 11 |
Sun
Sept 12 |
| Zone A |
No activity -
Labour Day
|
|
|
|
|
No activity |
No activity |
| Zone B |
|
|
|
|
| Zone C |
I
V
|
I
V
|
I
V
|
I
V
|
| Zone D |
V
G |
V
G |
V
G |
V
G |
*Shrouded impact hammers will be used to complete piles that cannot
be completed using the other piling methods alone as permitted by the
CTA order. In zones A, B, and C, when impact hammers are used, noise
barriers will be in place. Zone D does not permit the use of noise
barriers as space is restricted.
**denotes work that is part of the CP track
closure and has been approved by the CTA.
Archived Schedules
Project schedule and updates
Construction - Phase 2 (piling construction)
Total steel pipe piles driven to date: 2253 of 2338 (85 remaining)
GO has implemented several noise mitigation measures to lessen the
impact of the noise from this work on local residents and businesses.
These measures include noise shrouds placed around the machinery and the
installation of moveable sound barriers at the piling site. Since June
8, 2009, GO has voluntarily required that impact hammers, when used,
must be equipped with a noise shroud. The CTA decision placed additional
restrictions on the use of impact hammers effective December 22, 2009.
Impact hammers have not been used at all between December 21 and January
4, 2010, and when work begins again on January 5, shrouded impact
hammers will only be used for the limited use permitted by the CTA
decision.
The noise mitigation measures have been very effective in reducing
the noise disruption, but they have also resulted in a longer
construction schedule for Phase 2 works. The pile installation phase was
originally projected for completion in December 2009, with the
mitigation GO started using in June 2009 and in accordance with the
information previously distributed to the community, the piling contract
would have been extended. It was anticipated last November that the
piling would continue into the summer of 2010 due to the implementation
of these mitigation measures. With the recent decision imposed by the
CTA, piling will now be complete in late 2010. Following this phase of
the project, excavation will occur and the overall project is now
scheduled for completion in the fall of 2014.
Construction hours
The use of the vibratory hammer and impact hammers will be
restricted to the hours of 8:00 a.m. to 4:00 p.m. on weekdays only.
Giken technology may operate between 7:00 a.m. and 7:00 p.m. on
weekdays, and between 9:00 a.m. and 7:00 p.m. on Saturdays.
After December 18th, 2009, the use of impact hammers has been
limited and will be used only in conjunction with a PTC vibratory
hammer or only in exceptional circumstances where no other method is
possible.
The CTA decision affects only pile driving activities. Other
construction work that does not include pile driving will generally
occur between 7:00 a.m. and 7:00 p.m. on weekdays, and between 9:00
a.m. and 7:00 p.m. on Saturdays. On occasion, weekend and/or
overnight track work will be required.
Community Status Newsletter archive
Definitions
West Toronto Diamond Grade Separation – Definitions
Interlocking steel pipe piles: Pipe piles make up
the majority of the piles required for the West Toronto Grade
Separation. They provide the structural strength and the required water
tightness for the walls that will make up the structure for the lowered
track section.
Impact hammers: Impact hammers are the fastest, most
effective and reliable means of installing pipe piles. They provide a
high level of accuracy, which is important because of the tight corridor
dimensions and surrounding operational tracks. Impact hammers are also
the noisiest.
(Conventional) vibratory hammers: In the industry,
vibratory hammers are currently mostly used to remove piles out of
alignment and/or temporary piles, but can also be used for pile driving.
Vibratory hammers use vibration rather than impact to advance the pile;
therefore, they have more difficulty getting through dense soil
conditions at depth. Vibratory hammers are also less accurate with the
sites soil conditions and depths of piles required for this project.
Vibratory hammers do produce less noise; however, the vibration they
produce is constant and can be unsettling to residents of the
neighbourhood. The vibration levels produced by the vibratory hammer are
also more difficult to control. For these reasons, the conventional
vibratory hammer is only used for pre-work setup, and has not ever been
used on the project for actual pile installation.
Computer-controlled (French or PTC) vibratory hammer:
A unique computer-controlled vibratory hammer was brought in
from Europe for this project. This machine allows much greater control
of vibration levels, although when in use has caused some disruption in
the neighbourhood. Progress with the machine has been slow, and often it
has not been able to fully drive piles to the required depth.
Giken unit (or technology): This technology uses a
hydraulic press-in method. The machine is one of two in the world with
sufficient capacity to install the size of piles required for this
project. The Giken unit has some significant limitations. The machine
was brought in from Japan and was untested in the type of soil
conditions at this site. With a maximum production rate of up to two
piles per day, the project schedule will be significantly extended.
Shrouds: Hydraulically operated enclosures around
the impact hammer that muffle the noise from the hammer impacting the
pile, and the hammer itself. The shrouds are made using special sound
absorbing material resistant to high temperatures, and were custom
developed and fabricated for this project.
Noise walls: Sections of sound absorbing noise
barrier (used along highways) mounted on a moveable frame.
Depowering of the impact hammer: Reducing the power produced by the
hammer to soften the blow. This reduces the noise level by up to 10
decibels (50 per cent), but increases the number of blows needed to
install the pile.
Canadian Transportation Agency Order
West Toronto Diamond Grade Separation: Canadian Transportation
Agency Order
The CTA decision dictates ways and means of the types of
equipment used for pile driving, how the equipment is used, and when
equipment can be used. These restrictions will dramatically slow the
pace of the work, and the overall project is anticipated to take five
years (to fall 2014) to complete.
In accordance with the CTA decision, GO has restricted the use of
impact hammers and hours of pile driving activity as the December 7,
2009 decision is outlined below:
"Giken Hammer:
- extend the use of the Giken hammer for the duration of the steel
pipe pile-driving activities on the project and for more than the
previously scheduled 250 piles. To that end, GO Transit is required
to pursue an extension of the contract for the use of the Giken
hammer with the supplier for the duration of the pile-driving
activities. If GO Transit is not able to secure an extension to the
contract with the supplier, GO Transit is to notify the Agency, the
WTDCG, and the City of Toronto with an explanation of the reasons
why it was not possible to secure the extension.
- use the Giken hammer in more sensitive areas.
- use the Giken hammer, in addition to weekday pile-driving
activities, for pile-driving activities that take place outside the
standard hours of 8:00 a.m. to 4:00 p.m. on weekdays."
COMMENT: GO is required to pursue an extension
of the contract for the use of Giken. The current piling contract ends
on March 31, 2010 and GO can, through our general contractor, continue
to use Giken. Since September, GO has been using the Giken unit north of
the Old Weston Road crossing, next to the National Rubber Technologies
(NRT) building. Use of the Giken unit has been successful, but its
progress is also very slow. It will take over six months (to the end of
March 2010) to install the 250 piles, about 10 per cent of the total
number of steel pipe piles for this project.
"PTC-Vibro Hammer:
- Within 14 days from the date of this Decision, use a PTC-Vibro
hammer as the primary method to install the steel pipe piles by
augering them, if needed and where possible, to complete their
installation. Where complete installation with a PTC-Vibro hammer
and augering is not possible, drive the piles to the maximum depth
possible, considering soil conditions, with the PTC-Vibro hammer and
only then use an impact hammer to finish the pile-driving
activities. This does not preclude GO Transit from employing a
conventional vibratory hammer in areas that are less sensitive to
vibrations or where GO Transit can mitigate the impact of
vibrations."
COMMENT: As of December 21, the CTA ordered GO
to use the PTC vibratory hammer as the primary method to install steel
pipe piles. This direction is being complied with where possible,
although there are very few of the remaining piles that can be installed
with this equipment. This is because the PTC vibratory hammer often
cannot meet vibration limits set by City of Toronto by-laws or the
restrictive limits set by engineers.
"Impact Hammer and Related Mitigative Measures
- use an impact hammer on the project only in conjunction with a
PTC-Vibro hammer or where no other method is possible.
COMMENT: At a minimum, the impact hammer will
have to be used to install the final one to two metres of the pipe piles
as the PTC vibratory hammer cannot work close to or below ground level.
Previous experience with the PTC vibratory hammer determined that it was
often only able to install the pipe pile as little as halfway.
- where the impact hammer must be used, de-power the impact hammer
and decrease the hammer energy wherever possible and use shrouds,
skirts and rubberized chasers. If shrouds are opened, any opening
must be positioned, wherever possible, down the tracks and not
toward any residential area.
COMMENT: These noise mitigation measures have
been in place since June 8, 2009.
- where the impact hammer must be used, employ moveable noise
barriers, wherever possible, to deflect noise away from nearby
residential areas by moving them to current pile-driving locations."
COMMENT: This is already in place, although
noise barriers can only be used where they do not interfere with worker
safety or train operator sightlines.
"Limited Hours for Pile-Driving Activities
- use the Giken hammer, the preferred method of pile-driving,
between the hours of 7:00 a.m. and 7:00 p.m. on weekdays (excluding
statutory holidays) and between 9:00 a.m. and 7:00 p.m. on
Saturdays.
- restrict the hours of work for installing piles with the
PTC-Vibro, conventional vibratory and impact hammers to between 8:00
a.m. and 4:00 p.m. on weekdays.
- negotiate agreements with the City of Toronto to allow for road
closures such that pile-driving activities undertaken with the
PTC-Vibro, conventional vibratory and impact hammers are limited to
between 8:00 a.m. and 4:00 p.m. on weekdays.
- negotiate agreements with other railway companies to allow for
train blocks such that pile-driving activities undertaken with the
PTC-Vibro, conventional vibratory and impact hammers are limited to
between 8:00 a.m. and 4:00 p.m. on weekdays.
- on those exceptional occasions when pile-driving activities must
take place outside of the hours of 8:00 a.m. and 4:00 p.m. on
weekdays and it is not possible to use the Giken hammer, the
PTC-Vibro, conventional vibratory and impact hammers may only be
used following 14 days prior notice on GO Transit's Web site of the
proposed activity, including specific details of the constraints
that preclude the use of the Giken hammer. In addition, GO Transit
must report within its communication program the actual use of the
PTC-Vibro, conventional vibratory and impact hammers."
COMMENT: All restrictions as noted in the
limited hours of pile driving activities are being adhered to.
"Noise and Vibration Monitoring
- within 14 days from the date of this Decision, prepare and submit
to the Agency, for approval, a proposed methodology for an enhanced
noise and vibration monitoring program to provide weekly noise and
vibration level measurements, including equipment to be employed,
method of measurement and associated metrics, and the criteria for
selecting the location of measurements.
- at the same time as it submits its proposal to the Agency, provide
copies to the WTDCG and the City of Toronto, which will then have
seven days from receipt of the proposal to submit their comments
regarding the proposed methodology."
COMMENT: The CTA decision required GO to submit
for CTA approval a proposed program for noise and vibration monitoring
by December 22, 2009.
GO has retained the services of a specialist noise and vibration
consultant who provided assistance with the development of the ordered
noise and vibration monitoring program (submitted on December 21, 2009).
The proposal for the terms of reference for this program has been
submitted to the CTA, WTDCG and City of Toronto for review and comment.
Comments were requested for December 29, 2009. As of December 29, 2009,
the Agency has neither approved nor commented on the plan. The City of
Toronto commented on the plan as of December 30.
Once the CTA approves the plan, the implementation of the
required monitoring program will require two to six weeks beyond the
approval of the program as submitted. This is due to the public
tendering process and GOs ability to approve and secure a contract for
the supply and installation of the noise and vibration monitors, the
supply and installation of these monitors, in accordance with and when
the terms of reference that have been agreed to.
The proposal for the terms of reference for this program has been
submitted to the CTA, WTDCG and City of Toronto for review and comment.
Comments were requested for December 29, 2009.
"Communications
- within 7 days from the date of this Decision, post on the current
Web site and update daily all scheduled pile-driving activities for
the project and their location, as well as any scheduled periods of
inactivity (project plans) for a projected period of no less than 14
days from the date of posting, which project plans cannot be changed
except following notice as set out in c) below.
COMMENT: Implemented on December 14, 2009.
- within 28 days from the date of this Decision, consult with the
WTDCG and the City of Toronto, and implement, a more comprehensive
communication program, which must include:
- an enhanced Web site, which is updated daily, to communicate
information to local residents and businesses including, without
limitation, detailed information about the current pile-driving
activities and associated equipment on the site; the project plans
for a projected period of no less than 14 days from the date of
posting, which project plans which cannot be changed except
following notice as set out in c) below; and, the locations and
projected locations of moveable barriers and any constraints that
preclude the use of moveable barriers at any location; and
- an e-mail address and phone line, both to be answered by a person
knowledgeable about the project and its schedule, for residents and
businesses to communicate particular concerns about the current and
projected pile-driving activities and to which GO Transit must
investigate and respond within 48 hours.
COMMENT: Implemented on January 5, 2010 with
input received from the City of Toronto and individual community
members, but not the WTDCG.
- in the event of exceptional circumstances which necessitate a
temporary change in the project plans and prior to such change being
implemented, GO Transit is to post such change on the current, and
thereafter the enhanced, Web site, together with the anticipated
duration of the change and the reasons necessitating the change; and
if required, revise the project plans to reflect such change.
- within 14 days following the approval by the Agency of the noise
and vibration monitoring methodology, commence posting on the Web
site a weekly report containing the results of noise and vibration
measurements as well as an assessment of the effectiveness of
implemented mitigative measures; and, subject to compliance with
privacy protection legislation, any complaints received, and how
they were addressed and resolved."
COMMENT: Posting of complaints information is
implemented and an update on the status of the noise and vibration
monitoring program has been provided on January 4, 2010.
For a summary of the complete Canadian Transportation Agency Order of
Specific Corrective Measures, please see the CTA website posting.
Noise and vibration monitoring log
West Toronto Diamond Grade Separation: Noise and Vibration
Monitoring Log
GO has received approval for its proposed noise and vibration
monitoring program and implemented the program. The monitoring results
will be provided each week.
Noise and
vibration monitoring
results for the week of July 9 to July 13, 2010 are available.
Archived noise and vibration logs
|
Week |
Noise |
Vibration |
|
April 7 to April 12, 2010 |
download
pdf |
download pdf |
|
April 13 to April 19, 2010 |
download
pdf |
download pdf |
|
April 19 to April 26, 2010 |
download pdf |
download pdf |
|
April 26 to May 2, 2010 |
download pdf |
download
pdf |
|
May 3 to May 10, 2010 |
download pdf |
download pdf |
|
May 11 to May 18, 2010 |
download pdf |
download pdf |
|
May 18 to May 21, 2010 |
download pdf |
download pdf |
|
May 21 to May 28, 2010 |
download pdf |
download pdf |
|
May 28 to June 4, 2010 |
download pdf |
download pdf |
|
June 4 to June 11, 2010 |
download pdf |
download pdf |
|
June 11 to June 18, 2010 |
download pdf |
download pdf |
|
June 18 to June 25, 2010 |
download pdf |
download pdf |
|
June 25 to July 2, 2010 |
download pdf |
download pdf |
|
July 5 to July 9, 2010 |
download pdf |
download pdf |
|
July 9 to July 13, 2010 |
download pdf |
download pdf |
Noise and Vibration monitoring map

Comments log
West Toronto Diamond Grade Separation: Community Comments Log
Comments log from August 16 to 20, 2010
Date Received |
Response Date |
Received By |
Comments |
Action |
Zone |
|
17-Aug-10 |
17-Aug-10 |
On-site Community Liaison |
Inquired about noise and vibrations |
Explained that current work requires intermittent use of impact and
vibratory hammer and that vibration levels are being monitored. |
A |
|
17-Aug-10 |
17-Aug-10 |
On-site Community Liaison |
Inquired about general work schedule |
Explained that current work requires intermittent use of impact and
vibratory hammer and that project history is available on the
website. |
Outside of area |
Project Area Map and Zones

Comments Archive
Contact information
West Toronto Diamond Grade Separation: Contacts
West Toronto Diamond project pile driving and construction
comments and inquiries
Kathryn Hanford
West Toronto Diamond project on-site community liaison
Tel: 416.604.9582
Email:
Kathryn.Hanford@gotransit.com
Canadian Transportation Agency
Tel: 1.888.222.2592
TTY: 1.800.669.5575
Email: info@otc-cta.gc.ca
GO Transit (CTA Order)
Tel: 416-869-3200
Toll free: 1.888.438.6646
TTY: 1.800.387.3652
Email: info@gotransit.com
GO Media Relations
Vanessa Thomas
Media Relations and Issues Specialist
Tel: 416.874.5974
Email:
Vanessa.Thomas@metrolinx.com
Robin Alam
Media Relations and Issues Specialist
Tel: 416.874.5975
Email:
Robin.Alam@metrolinx.com